This report pertains to the progress of the Resettlement Action Plan (RAP) for Construction Package 2 and the Land Acquisition Plan (LAP) for Construction Package 3 of the Cebu Bus Rapid Transit (BRT)...
This report primarily covers the progress of the Resettlement Action Plan (RAP) for the Construction Package 2 of the Cebu Bus Rapid Transit (BRT) project covering the month of February 2024
The development objective of Cebu Bus Rapid Transit Project for Philippines is to improve the over-all performance of the urban passenger transport system in the Project Corridor in Cebu City in terms...
In compliance with the approved Resettlement Action Plan (RAP), specifically Chapter 11.2.3, of the Cebu Bus Rapid Transit (BRT), a monthly status report is hereby submitted to the BRT National Program...
The development objective of Cebu Bus Rapid Transit Project for Philippines is to improve the over-all performance of the urban passenger transport system in the Project Corridor in Cebu City in terms...