This report presents the results of a performance audit on The Turkey third and fourth Cukurova Power Projects. Both the Projects performing satisfactorily as well as performance of the beneficiary Cukurova...
The proposed project consists of the construction and installation of about 300 km of transmission lines, sub-stations at Tarsus, Payas and Antakya, and completion of the Kadincik II project financed out...
This press release announces on July 1, 1971, that the expansion of the largest private power company in Turkey, Cukurova Elektrik A.S. (CEAS), will be assisted by seven million US dollars World Bank loan...
The proposed project consists of the construction and installation of about 300 km of transmission lines, sub-stations at Tarsus, Payas and Antakya, and completion of the Kadincik II project financed out...