Ratings of Da Nang-Quang Ngai Expressway Development Project for Vietnam were as follows: outcome was moderately satisfactory, Bank performance was moderately satisfactory, and monitoring and evaluation quality was modest. Some of the lessons learned include: (i) Effective contract management of large value and complex contracts requires clear statements of obligations of contractors, sub-contractors and procuring agencies, close monitoring of contractors...
Подробнее
ПОДРОБНАЯ ИНФОРМАЦИЯ
-
2019/10/03
-
Отчет о завершении и результатах проекта
-
ICR4936
-
1
-
1
-
2019/11/04
-
Disclosed
-
Vietnam - Da Nang-Quang Ngai Expressway Development Project
-
Quality and Cost Based Selection