Ratings for the Programmatic Governance Reform and Growth Project for Sierra Leone were as follows: outcomes were satisfactory; risk to development outcome was substantial; Bank performance was satisfactory; and borrower performance was also satisfactory. Some lessons learned includes: in the case of Sierra Leone the Governance Reform and Growth (GRG) series helped to consolidate and entrench the local councils which were re-established after a 30...
Подробнее
ПОДРОБНАЯ ИНФОРМАЦИЯ
-
2012/01/31
-
Отчет о завершении и результатах проекта
-
ICR1761
-
1
-
1
-
2012/03/14
-
Disclosed
-
Sierra Leone - Programmatic Governance Reform and Growth Project
-
Administrative and Civil Service Reform
ФАЙЛЫ ДЛЯ СКАЧИВАНИЯ
ПОЛНЫЙ ОТЧЕТ
Официальная версия документа (может содержать подписи, и т.д.)