Ratings for the Water Utilities Efficiency Improvement Project for Mexico were as follows: outcomes were moderately unsatisfactory, the risk to development outcome was moderate, the Bank performance was satisfactory, and the Borrower performance was also satisfactory. Some lessons learned included: project design needs to take into account the limitations in the legal framework to introduce innovative delivery mechanisms (such as output-based disbursement)...