The development objective is to improve energy efficiency in heat and power generation in selected towns in Belarus. The project is reaching successful completion and will be closed on December 31, 2017. The project implementation has been consistently rated satisfactory. The PDO is expected to be achieved satisfactorily at project closing. All combined heat and power (CHP) plants financed by the original loan (US$125 million) are in commercial operation...
Подробнее
Document also available in :
Английский
ПОДРОБНАЯ ИНФОРМАЦИЯ
-
2017/12/22
-
Документ о проекте
-
RES30988
-
1
-
1
-
2017/12/22
-
Disclosed
-
Belarus - Energy Efficiency Project : restructuring
-
Energy Efficiency in Heat and Power