The overall outcome of the project is rated unsatisfactory, as it failed to fully achieve each of its four main objectives. The key lessons learned are: a) Over-ambitious project design and objectives should be avoided. b) An implementation timetable should take into account the administrative realities of the processes for appointing key project staff, mobilizing counterpart funds, and initiating activities with long lead times and the major deficiencies...