Pakistan - Balochistan Education Support Project (Английский)

The Balochistan Education Support Project for Pakistan received a moderately satisfactory outcome rating with high risk to development outcome. The Bank received a satisfactory rating for their performance while the Borrower received a moderately satisfactory rating. Three restructurings took place throughout the course of this project. The first restructuring extended the project closing date 18 months to allow completion of construction activities...