Ratings for the Second Skills Development Project for Afghanistan were as follows: outcome was moderately satisfactory, Bank performance was satisfactory, and monitoring and evaluation (M and E) quality was modest. Some lessons learned included: The Bank should caution clients from being overly ambitious and ensure a proper balance exists between the project objectives, targets, and the realities of the project context. The Bank team’s flexibility...