Performance aspects of eight World Bank financed irrigation projects are evaluated. Comparison of anticipated and realized costs and schedules reveal that construction costs are usually higher than anticipated and the execution of construction falls behind schedule. The combined effect is to reduce originally anticipated net benefits. However, the initial overestimate of anticipated net benefits, as indicated by the internal rate of return, is limited...