The development objective of the Electricity Supply Accountability and Reliability Improvement Project for Kyrgyz Republic is to improve the reliability of electricity supply in the project area and strengthen the governance of Severelectro’s operations. Some of the negative impacts and mitigation measures include: (1) construction of a new substation sport with two transformer units (2x16 MVA) is required to meet both current and projected demand...
Подробнее
Document also available in :
English|Russian
ПОДРОБНАЯ ИНФОРМАЦИЯ
-
2015/11/01
-
План переселения
-
SFG2190
-
1
-
1
-
2016/05/17
-
Disclosed
-
Kyrgyz Republic - Electricity Supply Accountability and Reliability Improvement Project : resettlement plan
-