Jamaica - Generation Recovery and Improvement Project (Английский)

The project outcome is rated "unsatisfactory". Major components were not completed and the sustainability of project results is uncertain, notwithstanding the successful rehabilitation of generation facilities, including costs and outages reduction. The Bank's performance for project identification/preparation is rated "satisfactory"; however, for appraisal/supervision it is rated "unsatisfactory". Even though the Bank responded expeditiously to an...