China - Shandong Power Plant Flue Gas Desulfurization Project (Английский)

The China Shandong Power Plant Flue Gas Desulfurization Project was rated as follows: outcomes were unsatisfactory, risk to development outcome was moderate, and both Bank and borrower performance were unsatisfactory. The lessons learned during this project are - (1) A project supporting mandatory targets should carefully time project support with the targets' timeline. (2) Early communication to the final borrowers of the Bank's project cycle...