Ratings for the Second Liaoning Medium Cities Infrastructure Project for China were as follows: outcomes were moderately satisfactory, risk to development outcome was moderate, Bank performance was moderately satisfactory, and Borrower performance was moderately satisfactory. Some lessons learned included: build strong partnership between all stakeholders including the Bank, the Borrower, and the implementing agencies while recognizing their cultural...
Подробнее
ПОДРОБНАЯ ИНФОРМАЦИЯ
-
2015/12/23
-
Отчет о завершении и результатах проекта
-
ICR3237
-
1
-
1
-
2015/12/28
-
Disclosed
-
China - Second Liaoning Medium Cities Infrastructure Project
-
infrastructure and service delivery