The project consists of the main elements of SEGBA's investments in transmission lines, substations and distribution facilities in the Greater Buenos Aires region for the years 1977-1981, and the preparation of a national power expansion plan and a national power sector organization study, both to be carried out by the Government.
Подробнее
ПОДРОБНАЯ ИНФОРМАЦИЯ
-
1976/09/30
-
Отчет персонала об оценке проекта
-
675
-
1
-
1
-
2010/06/18
-
Disclosed
-
Argentina - Fourth Buenos Aires Power Project
-
financial ratio