This is a performance audit of the Second SEMRY Rice Project. The First SEMRY Rice Project was implemented with only minor delays and a small cost overrun. The project got off to a quick start and generally proceeded on schedule during the first three years. However, two problems arose: the reservoir embankment dike experienced serious erosion and seepage problems, and an imbalance developed between land available for cultivation and actual land use...