Ratings for the Second Water Sector Investment Project for Tunisia were as follows: outcomes were unsatisfactory, the risk to development outcome was substantial, the Bank performance was unsatisfactory, and the Borrower performance was also unsatisfactory. Some lessons learned included: the project will have greatly benefited from a solid institutional analysis. Such an analysis, possibly in the form of ASA, will have provided all stakeholders with...
Подробнее
ПОДРОБНАЯ ИНФОРМАЦИЯ
-
2015/09/30
-
Отчет о завершении и результатах проекта
-
ICR3494
-
1
-
1
-
2015/11/17
-
Disclosed
-
Tunisia - Second Water Sector Investment Project
-
Institutional Strengthening and Capacity Building
ФАЙЛЫ ДЛЯ СКАЧИВАНИЯ
ПОЛНЫЙ ОТЧЕТ
Официальная версия документа (может содержать подписи, и т.д.)