Skip to Main Navigation

Pakistan - First Phase of the Dasu Hydropower Project : Resettlement Plan (Vol. 1 of 4) : داسو ٹرانسمیشن لائن پروجیکٹ کے لئے دوبارہ آبادکاری ایکشن پلان : مختصر خلاصہ (Урду)

The development objective of the First Phase of the Dasu Hydropower Project for Pakistan is to facilitate the expansion of electricity supply of hydro-power in Pakistan. Some of the negative impacts and mitigation measures include: (1) Pakistani rupee (PKR) 1,120,000 for each tower as compensation for the land taken for each tower. The amount may vary from on one tower to another due to location and a variety of other factors; (2) cash compensation...
Подробнее

ПОДРОБНАЯ ИНФОРМАЦИЯ

  • 2019/11/01

  • План переселения

  • SFG5872

  • 1

  • 4 (См. все тома)

  • Пакистан,

  • Южная Азия,

  • 2019/11/21

  • Disclosed

  • داسو ٹرانسمیشن لائن پروجیکٹ کے لئے دوبارہ آبادکاری ایکشن پلان : مختصر خلاصہ

This document is being processed or is not available.