Sudan - Power Project (Английский)

The project, which forms part of a major expansion program planned by CEWC, will consist of the construction of a superstructure on the existing foundation of a power house and the installation of three 30 MW water turbine generating units at the Roseires dam; the construction of 490 km 220 kv and 16 km 110 kv transmission lines, including associated substations, principally to connect the Roseires station with Khartoum; the installation of a 15 MW...