Ratings for the Third East West Highway Improvement Project for Georgia were as follows: outcomes were satisfactory, risk to development outcome was moderate, Bank performance was moderately satisfactory, and Borrower performance was moderately satisfactory. Some lessons learned included : importance of the engineering designs review. there is a need to consider the reinstatement of access to local traffic during project design stage. The Implementing...