The project outcome is rated satisfactory, sustainability likely, though the institutional development impact was negligible. Lessons highlight the following. The project illustrates well that institutional, and financial improvements are far more difficult to achieve than civil works; thus, project design should carefully consider the risks of financing, e.g., hardware and software as in this case, to avoid regretting high financial costs, and rather...
Подробнее
ПОДРОБНАЯ ИНФОРМАЦИЯ
-
2002/06/28
-
Отчет о завершении и результатах проекта
-
24070
-
1
-
1
-
2010/06/18
-
Disclosed
-
Morocco - Fifth Water Supply Project
-
overseas economic cooperation fund