This is a performance audit of the Second SEMRY Rice Project. The First SEMRY Rice Project was implemented with only minor delays and a small cost overrun. The project got off to a quick start and generally proceeded on schedule during the first three years. However, two problems arose: the reservoir embankment dike experienced serious erosion and seepage problems, and an imbalance developed between land available for cultivation and actual land use...
Подробнее
Document also available in :
Английский
ПОДРОБНАЯ ИНФОРМАЦИЯ
-
1984/06/25
-
Доклад об оценке результатов деятельности по проекту
-
5156
-
1
-
1
-
2017/10/31
-
Disclosed
-
Cameroun - Deuxième Projet Rizicole de la Semry
-
Drainage systems