Ratings for the Rehabilitation Loan Project in Lithuania are as follows: overall outcome of the project was rated as fully satisfactory, and the performance of the Bank and the Borrower were rated as fully satisfactory. Some of the lessons learned from the project are: 1) the appointment of advisors to the project implementation unit (PIU), to provide overall project management support and expertise on procurement and disbursement, is critical to...