Ratings for the Geothermal Power Generation Project for Djibouti were as follows: outcome was moderately unsatisfactory, Bank performance was moderately satisfactory, and monitoring and evaluation (M and E) quality was substantial. Some lessons learned included: availability of pre-assessment of sufficiently accurate geothermal resource data can be a determining factor in project design. A pre-feasibility study carried out by a reputable geothermal...