Kenya - Electricity Expansion Project : Second Progress Report on the Implementation of Management's Action Plan (Английский)

On November 13, 2014, a request for inspection, submitted by members and representatives of a Maasai community that was resettled due to the project-supported geothermal developments in the Greater Olkaria Geothermal Area, was registered by the World Bank’s inspection panel. Management submitted its response to the request on December 19, 2014. Following Board approval of the panel’s recommendation on February 13, 2015, the inspection panel undertook...