Ratings of Somali Petroleum Technical Assistance Project were as follows: outcome was moderately satisfactory, Bank performance was satisfactory, and monitoring and evaluation quality was modest. Some of the lessons learned include:(i) The overall implementation risk of this first small recipient executed project was set as high; (ii) The experience of the PMU Procurement Specialist and Financial Specialist with the Bank processes and procedures in...