Ratings for the Andhra Pradesh Disaster Recovery Project for India were as follows: outcome and Bank performance was moderately unsatisfactory and monitoring and evaluation (M and E) quality was modest. Some lessons learned included: in cases where the Project Management Unit (PMU) and implementing agency is also the entity responsible for emergency response, it is critical to preemptively augment its capacity to ensure implementation continuity in...
Подробнее
ПОДРОБНАЯ ИНФОРМАЦИЯ
-
2022/10/20
-
Отчет о завершении и результатах проекта
-
ICR5670
-
1
-
2022/10/26
-
Disclosed
-
India - Andhra Pradesh Disaster Recovery Project