The objective of the Enhancing Energy Security through Power Interconnection and Renewable Energy Program as First Phase of a Multi-Phase Programmatic Approach (MPA) is to enhance the implementation readiness of the Black Sea Submarine Cable (BSSC) Project. There are two components to the project, the first component being black sea seabed surveys. This component would finance (a) the surveys of the Black Sea seabed (seabed surveys), (b) the supervision...
Подробнее
ПОДРОБНАЯ ИНФОРМАЦИЯ
-
2024/04/25
-
Акт экспертизы проекта
-
PAD00201
-
1
-
2024/05/03
-
Disclosed
-
Simultaneous Disclosure
-
2024/05/20
-
Georgia - Enhancing Energy Security through Power Interconnection and Renewable Energy Program as First Phase of a Multi-Phase Programmatic Approach (MPA)
ФАЙЛЫ ДЛЯ СКАЧИВАНИЯ
ПОЛНЫЙ ОТЧЕТ