Ratings for the Electricity Access Services Expansion Project for Democratic Republic of Congo were as follows: outcomes were moderately satisfactory, the Bank's performance was moderately satisfactory, and the monitoring and evaluation quality was modest. Some lessons learned included: Activities aimed at rehabilitating the Mobayi Hydropower Plant and the associated transmission and distribution network in Gbadolite were fully canceled eight months...