Ratings for the Second Capacity Building in Public Financial Management Project for Kyrgyz Republic were as follows: outcome was moderately satisfactory, Bank performance was satisfactory, monitoring and evaluation (M and E) quality was substantial. Some lessons learned included: in complex institutional environments with low client capacity, project designs should be simpler and less ambitious and provide realistically sufficient (or extra) time...
Подробнее
ПОДРОБНАЯ ИНФОРМАЦИЯ
-
2023/02/20
-
Отчет о завершении и результатах проекта
-
ICR6150
-
1
-
2023/03/13
-
Disclosed
-
Kyrgyz Republic - Second Capacity Building in Public Financial Management Project