DETAILS
-
2022/07/31
-
Environmental Assessment
-
SFG5946
-
4
-
2022/08/21
-
Disclosed
-
Turkiye - Renewable Energy Integration Project : Environmental Assessment - Environmental and Social Management Plan for 154 kV Antalya GIS Substation, Muratpasa
DOWNLOADS
COMPLETE REPORT
Official version of document (may contain signatures, etc)
*The text version is uncorrected OCR text and is included solely to benefit users with slow connectivity.
Citation
Borrowing Agency.
Turkiye - Renewable Energy Integration Project : Environmental Assessment - Environmental and Social Management Plan for 154 kV Antalya GIS Substation, Muratpasa (Vol. 4) (Turkish). Turkiye : Borrowing Agency. http://documents.worldbank.org/curated/en/099015208212213939