This paper presents a statistical study of the geothermal resource risk in Indonesia, specifically, that the resource base and well productivity are adequate and that the drilling cost per well is reasonable. This paper is timely because the Government of Indonesia is now embarking on an ambitious plan to rapidly scale up geothermal power capacity and eventually achieve a longer-term target of 9,500 MW by 2025. This study relies on the resource base...